Yet another innovative milestone was achieved with the full completion of two HUME BOX GIRDER PEDESTRIAN BRIDGESat Pandan Perdana and Star-LRT Bandar Tasik Selatan, Kuala Lumpur.
The move to install pedestrian bridges was initiated to provide a safe link for pedestrians along both sides of the busy highway. Installation of the bridge took no more than 6 hours at night to complete two spans and traffic flow was back to normal the following morning after construction.
Hume
Pretensioned Box Girder
Span length : 10
- 29m
Live load :
5 kN/m
Superimposed dead load 2
kN/m2
W :
2300 - 2500mm
B :
800 - 1000mm